RUSSIA: Ural Locomotives is advancing development of the prototype EVS360 Bely Krechet (White Gyrfalcon) high speed trainset, with Russian Railways expecting it to be delivered for testing during 2027.
The Bely Krechet project being undertaken by Sinara Group’s Ural Locomotives subsidiary in partnership with mostly Russian suppliers covers the development and production of 43 eight-car trainsets for the planned Moskva – St Petersburg high speed line. Two prototype trainsets are to be produced ahead of the 41 production units, with deliveries scheduled for 2028-30.
The EVS360 is intended for operation at up to 360 km/h, with a maximum design speed of 400 km/h. The eight-car train will accommodate approximately 454 passengers in four classes, with a bistro car also provided. It will be equipped with asynchronous traction motors and designed for operation under both 3 kV DC and 25 kV 50 Hz electrification supplies.
Assembly of the first trainset began in 2025, and by February this year the manufacturer had completed welding the aluminium bodies of the first motorised driving car and an intermediate trailer car. In September, structural strength tests were conducted on the bodies of the leading and intermediate cars, including tests to assess their energy absorption in collisions.
The first prototype is scheduled to undergo initial testing at the manufacturer’s facilities before moving to the Shcherbinka test centre near Moscow. Dynamic testing on new high speed infrastructure between Zelenograd and Tver is envisaged for autumn 2027. Commercial services are planned to start in April 2028.
The production schedule envisages 11 trainsets being completed in 2028, 29 in 2029 and the remaining three in 2030. The planned service life is 30 years.