Safety and strengthening work on Scabbing Flat Bridge has been completed with temporary width restrictions removed and the load limit increased from 42.5 tonnes to 43.5 tonnes after a change in the heavy vehicle mass limits framework.

Work on the historic timber bridge on Arthurville Road, Geurie has been carried out in stages since a routine inspection in late 2023 identified significant deterioration to the structure.

AdvertisementIn-article

Crews have replaced ageing and deteriorated timber within the bridge structure, installed temporary structural supports, repaired bridge piers and replaced cross girders, stringers and truss members.

A temporary Bailey bridge used intermittently to support the bridge structure while truss rehabilitation work was carried out resulted in a narrowing of the lane width to 3.4 metres but allowed the previous full 42.5-tonne capacity to remain in place during much of the work.

Transport for NSW Executive Director Damien Pfeiffer said removal of the Bailey bridge had signalled the end of strengthening work and seen Scabbing Flat Bridge return to its normal load and width capacities.

“We acknowledge the inconvenience that a series of temporary load restrictions, width restrictions and detours over the past three years have caused for the community but ensuring the ongoing safety and stability of Scabbing Flat Bridge has remained the number one priority,” Mr Pfeiffer said.

“Transport for NSW thanks the Geurie community, local farmers, freight operators and motorists for their patience while this extensive program of work has been carried out.

“In total, more than 80 bridge timber members identified during inspections have now been replaced, giving a clear indication of the scale of the rehabilitation work needed on the bridge.”

Scabbing Flat Bridge, built in 1910, is a timber truss bridge identified for retention under the Timber Truss Bridge Conservation Strategy (2012).

A routine inspection in late 2023 revealed significant deterioration of the timber structure and evidence of active termites, requiring the immediate introduction of a reduced 16-tonne load limit to protect the bridge and road users while planning for repairs began.

Essential safety work started in July 2024 and a temporary Bailey bridge was installed to support the structure during rehabilitation of the bridge trusses

The bridge returned to its full 42.5-tonne load capacity in October 2025 while the remaining rehabilitation work continued. Since then changes to the heavy vehicle mass limits framework have allowed the bridge capacity to be increased to 43.5 tonnes.

As a retained timber truss bridge, Scabbing Flat Bridge will still require regular routine maintenance to ensure its ongoing safety.

In September 2026, Transport for NSW launched a review of the Timber Truss Bridge Strategy and invited communities across NSW to provide their feedback on how well the strategy supported safe, efficient regional roads, how significant heritage structures could be appropriately preserved, and any changes they would recommend to improve the existing strategy.

Feedback closed on Friday 30 October and responses from Transport for NSW and the public will help inform a draft revised strategy.

A second round of consultation on the draft revised strategy is planned for mid to late 2027.